Fairmount Avenue Green Street Project
This notification is to inform you of the NewarkDIG/Rutgers Water Resources Program green infrastructure installation at the corner Fairmount and 16th Avenues. This work is designed to capture stormwater and reduce the burden on our sewer system while adding greenery and beautification.
This work is set to begin on or around November 12, 2025 and continue until mid-December 2025 or early January 2026, depending on weather conditions. Additional planting in the area may continue starting in Spring 2026, depending on weather conditions.
Fairmount Avenue Green Street
Expected Construction Impacts:
-
Estimated two months of construction
-
Use of heavy machinery during construction
-
Demolition and excavation may cause noise and dust
-
Installation of piping and concrete may cause noise, dust and vibrations
-
Partial closure of Fairmount Ave and 16th Ave at times during active work hours
-
Temporary parking restrictions during construction
-
No disruptions to garbage or recycling pick up are expected
Phase 1 and Phase 2 Implementation Project
Phase 1 and 2 Rendering
The rendering on the right displays the intersection of Fairmount Avenue and 16th Avenue. The intersection will be extended to include 1,854 SF stormwater planters, managing stormwater runoff from 51,685 SF roadway.
​
Existing ADA Accessible ramps and crosswalks will reman intact and new roadway striping and flexible delineators will surround the proposed curb-line extension.
​
Planter Box Rendering
The rendering details the filtration and stormwater collection the green street project is doing below the surface.